Tailings dam job standard

1 Subject content

This standard specifies the operating capacity, responsibility, authority and safe operation procedures of the tailings dam.

2. area

This standard applies to the tailings dam post personnel and their inspection and assessment.

3 job ability requirements

3.1 Passed the training of the post and the third-level safety education.

3.2 Have a junior high school education or above.

3.3 Obtain the operator of the special post operation of the tailings dam.

3.4 Have certain equipment operation experience, familiar with the distribution of pipelines within the scope of this post, tailings facilities and their distribution structure.

3 Responsibility

4.1 Responsible for its own safety.

4.2 Responsible for the safety supervision of non-workshop personnel entering the tailings dam. .

4.3 Guarantee the safe discharge of tailings from the plant.

4.4 Ensure that the shaft overflow reaches the discharge standard.

4.5 Ensure the safe operation of the tailings dam.

4 permissions

5.1 The right to prevent non-workshop workers from entering the work area.

5.2 The right to prevent employees who are not wearing protective products from entering the work area.

5.3 Have the right to prevent illegal command and illegal operation.

6.1   Dangerous source of this position

6.1.1 Potential tailings pond water operations in the working area.

6.1.2 Pay attention to its own safety, especially at night inspections and entering vertical shaft operations.

6.2 Safety Precautions and Control Measures

6.2.1 Observe the surrounding working environment, walk and watch the foot slip under the foot.

6.2.2 Wear labor protection articles in strict accordance with the requirements, and the working pontoons meet the safety standards.

6.2.3 All kinds of objects or tools in the production site must be placed neatly and safely. It should be regularly checked and implemented, and beware of accidents.

6.2.4 Pay attention to and carefully check the power supply line, actively control the unsafe state of the object, ensure safe use of electricity, and pay attention to fire prevention.

6.2.5 Do a good job of controlling your own unsafe behaviors, and you should adhere to regularity and achieve standardized operations.

6.3 Environmental factors of this post

6.3.1 Pipeline and valve wear cause tailings spillover

6.3.2 Post sanitary waste is not cleaned and cleaned up.

6.4 Environmental Considerations and Control Measures

6.4.1 Strengthen inspection and timely treatment, pipeline and valve leakage.

6.4.2 Strengthen the inspection and pay attention to the length of the tailings pond.

6.4.3 Clean the post health in a timely manner.

7.5 Operating procedures

7.5.1 Before the flood season, flood discharge and drainage facilities must be comprehensive, especially the key parts such as inlet and outlet, which should be repeatedly inspected and found to be promptly disposed of;

7.5.2 Prepare necessary rescue materials, tools and equipment. Maintenance and refurbishment of roads leading to the tailings pond and roads on the dam, and ensuring safety and smoothness;

7.5.3 Strengthen the duty and inspection, the flood discharge (water) port must be guarded by special personnel, closely monitor the water regime change of the reservoir and the surface runoff dynamics of the gully on both sides of the dam, report the dangerous situation in time, and take urgent measures to prevent the situation from deteriorating. Leading to a broken top dam;

7.5.4 Calculate the maximum flood level and water edge position of the reservoir in the flood season according to the storage capacity, the catchment area, the flood season and the discharge capacity, and combine the ultra-high and sedimentary beach length, slope and slope shape required for safety. In case of slope seepage, etc., comprehensive consideration should be given to formulating a safe ferry scheme for tailings ponds, and if necessary, appropriate safe and reliable emergency flood discharge measures should be taken to prevent problems before they occur;

7.5.5 Open the water inlet above the normal water level of the flood discharge (water) structure to a certain height, and if necessary, reduce the water storage line must be unimpeded and fully exert the flood discharge efficiency;

7.5.6 A conspicuous, clear and secure water level observation scale shall be set up in the library and linked to the absolute elevation;

7.5.7 After the flood, the dam body and the flood discharge (water) structure pipe trenches and weak links shall be carefully inspected and cleaned. If problems are found, they shall be repaired or reinforced in time, and the tailings pond shall be kept at a high water level as much as possible. Free up the storage capacity and prevent floods from coming.